2023-08-02

【事務組公告】Notice of Construction Work 112年08月06日太陽光電發電設備施工公告

Written by

主旨:因「雲林縣、嘉義縣中央機關公有屋頂聯合標租」案」太陽光電發電設備租賃併聯施工作業需要,112年8月6日(日) 綜一館、綜二館將暫停供電,特此通知。

Subject:Due to the construction of solar installations , the power supply of the first assembly building and the second assembly building will be temporarily suspended on Aug. 6th.

 

【說 明 Instructions】

一、暫停區域 The area of power outage:
日期:112年 8月6日(星期日)
地點:綜一館、綜二館,停電時間:08:00-17:00

Date:Aug. 6th  , Sun.
Area and Time:The First assembly building and the Second assembly building from 08:00 to 17:00.

二、惠請轉告周知並請於停電時間前及早關閉相關用電設備,如:電腦設備等避免送電時發生不可預期損壞,廁所用水及飲用水如有需要請事先儲水備用。
Please inform the public and turn off the relevant electrical equipment such as computer equipment as early as possible before the power outage time so as to avoid unexpected damage after the power supply. The water for drinking and washing (toilet) might also be preserved in advance.


三、停電期間內,為避免發生不可預期事故,請勿搭乘電梯及啟動電氣設備。
During the suspension of the power supply, in order to avoid unforeseen accidents, please do not start electrical or computer equipment or take elevators.


四、如工程提前完工,將提早送電;惟倘工作發生特殊困難,可能延緩送電,不便之處,請 諒察。
If the project is completed ahead of schedule, the power should be delivered earlier; however, if there are difficulties in the work, the power delivery may be delayed. We apologized for any inconvenience.


五、若遇特殊情形無法工作時,將取消此次停電,待下次停電日期決定後,再另行奉告。
In case of failure to work under certain circumstances, the power outage will be postponed until further notice.


六、連絡人員 Contact person:
林先生 Mr. Wang:05-6315201 總務長室
韓先生 Mr. Han :0903-121689 (施工廠商)

總務處 敬上

112.08.02